On November 3, voters in Ashville, Ohio, were asked whether to keep their village council’s deal with the data center developer, EdgeConneX. The company has plans to build two data center buildings in the village and an 800 MW gas plant to power them. Voters rejected the deal, 1,469 to 331.
Sixteen days later, the Ohio Power Siting Board approved the gas plant, according to our permit tracker at Cleanview.
At the same meeting, the board approved a second, larger plant: the 1,350 MW Fairfield Energy Center, which Advanced Power is developing for a Vantage data center campus east of Columbus.
Together, the two plants more than doubled the on-site gas capacity Ohio has permitted for data centers, from 1.3 GW to 3.5 GW, according to Cleanview’s gas plant tracker.
Neither plant will connect to the grid. EdgeConneX’s Ashville plant will run on 66 gas engines and eight turbines, according to its application, and all of its power will go to the data center next door.
Ohio is the second state this month where on-site gas plants have been permitted ahead of a governor who campaigned on a pause. As we wrote last week, Texas recently approved about 5 GW.
The next governor will control the board
Amy Acton won the governor’s race the same night Ashville voted on their agreement with EdgeConneX. She campaigned on a “conditional moratorium“ on data centers and takes office on January 11.
Five of the siting board’s seven voting seats belong to the directors of state agencies. Those directors are appointed by the governor, and their terms end when the governor’s does. Acton will name their replacements.
In her campaign, Acton said data centers “must invest in their own energy generation options.” Her platform adds, “We will prioritize low cost, carbon-free and net-zero energy options, accompanied by storage options.”
Acton hasn’t said how she would impose a moratorium. Much of what she wants requires the legislature, where Republicans kept their majorities.
Two more plants are waiting for approval
Two more on-site gas plants are awaiting a decision from Ohio’s Siting Board: Williams’ 500 MW Neo plant for Meta and EdgeConneX’s 440 MW PowerConneX III. Both are near New Albany, and both have finished their hearings. Either could be approved before Acton takes office.
In Ashville, opponents have 30 days to ask the board to reconsider and have said they will appeal. The plant also needs an air permit from Ohio’s environmental regulator. And it needs a gas pipeline, which requires its own approval from the siting board. That decision will likely fall to Acton’s appointees.