The gap between a construction start and an energized campus is where these numbers will get tested. Step-up transformers are still quoted at 100 to 150 weeks, so a Q1 start lands online in 2028 or later no matter how fast the permits move, and the starts data will look recovered well before any load shows up on a grid.

James Marlow's avatar

Starts can slow, but on PJM (the grid for all or parts of 13 states and DC) power bills are already priced for demand that hasn't arrived. More than three quarters of the 21,470 megawatts of data center demand in PJM's forecast is growth still to come, and PJM's market monitor puts $12.8 billion of data center cost in capacity charges set for June 2027 to May 2029. Does your dataset show how much of the Q3 dip was in PJM states?